| STATUS
OF THE MAJOR COMPONENTS OF THE SARDAR SAROVAR PROJECT AT PRESENT
IS AS UNDER |
|
MAIN DAM
|
| a) |
The
Spillway of Sardar Sarovar Dam is raised upto its crest level
of 121.92 M. |
| b) |
65.76 LCM concrete has been placed against the total quantity
of 68.20 LCM in the dam which is about 96.43%. |
| c) |
Construction
of Irrigation Bye Pass Tunnel [IBPT] is almost completed. |
| d) |
Preconstruction activities of Garudeshwar weir has been taken
up. |
|
HYDRO
POWER
|
|
a)
|
CANAL
HEAD POWER HOUSE [CHPH] |
| There
are total 5 Units of Turbine Generator (TG) in CHPH, each of
50 MW installed capacity. All five units of Canal Head Power
House has been
commissioned |
| b) |
RIVER
BED POWER HOUSE [RBPH] |
| There
are total 6 units of Turbine Generator (TG) in RBPH, each of
200 MW installed capacity. All six units has been
commissioned |
|
|
|
CANAL
SYSTEM
|
|
MAIN
CANAL
|
|
Work
of Narmada Main Canal (NMC) from ch. 0 to 458 km is completed
except three Canal Syphon viz. Saraswati, Khari-II and Banas.
Work of these Canal Syphon is in progress. Water is flown
in Canal up to 458 Km. i.e. Rajasthan Border.
|
|
BRANCH
CANALS
|
|
Branch canals
offtaking from NMC Ch 0 to 263 km
|
|
Work of all the
22 Branch Canals off taking through this reach is completed. |
|
Saurashtra
Branch Canal [SBC] and its Sub Branches
|
|
Work of 90 km of SBC is completed and work in the remaining
reach is in progress. Work of 3 sub branches is completed
and work of 4 sub branches is in progress. Out of five Pumping
Stations on SBC-PS-1 is commissioned and the work of remaining
four Pumping Stations is in progress.
|
|
Branch
Canals of NMC reach between ch 263 to 458 km
|
|
Civil
work of Viramgam-I, Viramgam-II, Kharaghoda and Zinzuwada
branch canals are completed and installation of gates is under
progress. Work
of Goraiya, Bolera, Rajpura, Amarapura and Radhanpur is under
progress.
|
|
Kachchha
Branch Canal [KBC]
|
|
Work
of 25 Km. length of Kachchh Branch Canal is completed and
work in further 51 Km. is in progress. Detailed project report
for three Power stations are under preparation. Tenders for
three pumping stations are invited.
|
|
DISTRIBUTION SYSTEM |
|
Work
of distribution system in reach 0 to 312 Km. of NMC (except
command area of SBC) is in full swing.
|
|
CAD
WORKS
|
|
Work
of Command Area Development in 4,85,995 Ha. is in full swing.
Out of this work , in 3,00,083 Ha. has been completed.
|
|
The
height of Main dam will be raised from time to time subject
to necessary clearance. Canals and other works will be completed
in phases. It is expected that the entire project will be
completed by 2009-10.
|
|
INVESTOR
COMPLAINTS
|
|
1.
|
Pending
at the beginning of the quarter |
0
|
|
2.
|
Recived
during the quarter |
75
|
|
3.
|
Disposed
off during the quarter |
75
|
|
4.
|
Lying
unresolved at the end of quarter |
0
|
|