CURRENT STATUS OF THE PROJECT
STATUS OF THE MAJOR COMPONENTS OF THE SARDAR SAROVAR PROJECT AT PRESENT IS AS UNDER

MAIN DAM

a) The Spillway of Sardar Sarovar Dam is raised upto its crest level of 121.92 M.
b) 65.76 LCM concrete has been placed against the total quantity of 68.20 LCM in the dam which is about 96.43%.
c) Construction of Irrigation Bye Pass Tunnel [IBPT] is almost completed.
d) Preconstruction activities of Garudeshwar weir has been taken up.
HYDRO POWER
 a)
CANAL HEAD POWER HOUSE [CHPH]
There are total 5 Units of Turbine Generator (TG) in CHPH, each of 50 MW installed capacity. All five units of Canal Head Power House has been commissioned
b) RIVER BED POWER HOUSE [RBPH]
There are total 6 units of Turbine Generator (TG) in RBPH, each of 200 MW installed capacity. All six units has been commissioned

CANAL SYSTEM

MAIN CANAL

Work of Narmada Main Canal (NMC) from ch. 0 to 458 km is completed except three Canal Syphon viz. Saraswati, Khari-II and Banas. Work of these Canal Syphon is in progress. Water is flown in Canal up to 458 Km. i.e. Rajasthan Border.

BRANCH CANALS

Branch canals offtaking from NMC Ch 0 to 263 km

Work of all the 22 Branch Canals off taking through this reach is completed.
Saurashtra Branch Canal [SBC] and its Sub Branches
Work of 90 km of SBC is completed and work in the remaining reach is in progress. Work of 3 sub branches is completed and work of 4 sub branches is in progress. Out of five Pumping Stations on SBC-PS-1 is commissioned and the work of remaining four Pumping Stations is in progress.
Branch Canals of NMC reach between ch 263 to 458 km
Civil work of Viramgam-I, Viramgam-II, Kharaghoda and Zinzuwada branch canals are completed and installation of gates is under progress. Work of Goraiya, Bolera, Rajpura, Amarapura and Radhanpur is under progress.
Kachchha Branch Canal [KBC]
Work of 25 Km. length of Kachchh Branch Canal is completed and work in further 51 Km. is in progress. Detailed project report for three Power stations are under preparation. Tenders for three pumping stations are invited.
DISTRIBUTION SYSTEM
Work of distribution system in reach 0 to 312 Km. of NMC (except command area of SBC) is in full swing.
CAD WORKS
Work of Command Area Development in 4,85,995 Ha. is in full swing. Out of this work , in 3,00,083 Ha. has been completed.
The height of Main dam will be raised from time to time subject to necessary clearance. Canals and other works will be completed in phases. It is expected that the entire project will be completed by 2009-10.
INVESTOR COMPLAINTS
1.
Pending at the beginning of the quarter
0
2.
Recived during the quarter
75
3.
Disposed off during the quarter
75
4.
Lying unresolved at the end of quarter
0

LCM = LAC CUBIC METER
LSM = LAC SQUARE METER
THCM = THOUSAND CUBIC METER 
MAF = MILLION ACRE FEET
 

Designed & Maintained by :

SARDAR SAROVAR NARMADA NIGAM LTD.

Copyright © 01-02 - Sardar Sarovar Narmada Nigam Ltd. All rights reserved.