List of Dates and Events
Calender of Events pertaining to Area Of Dam covering the milestone achieved
Sr. # Date of Event Milestone achieved
1 15.12.83 & 23.2.84 Non overflow dam (1 to 10 blocks) foundation excavation and concrete work started.
2 In the year 1987 (April) Ministry of Enviornment & Forest, Govt. of India has given clearance to the project.
3 24.04.1987 Main Dam tender awarded and excavation started.
4 03.06.1987
Late Honourable Prime Minister Shri Rajiv Gandhi
has visited Kevadia Colony.
5 23.02.1994
Construction sluices of block no. 35 & 36 closed
at EL 18.0 m.
6 In March-1994
A writ petition was filed by NBA (Narmada Bachao
Andolan)
7 07.09.1994
24 lakh cusecs High flood in the River.
8 05.05.1995
Hon'ble Supreme Court restricted the dam height at
EL 80.30 m.
9 18.02.1999
Hon'ble Supreme Court permitted dam height upto EL
85.0 m.with 3.0 m hump. The target achieved on
15.4.1999. The Construction of 3.0 m hump
completed on 14.6.1999.
10 11.10.2000
Permission for construction of Irrigation Bye Pass
tunnel.
11 18.10.2000
Hon'ble Supreme Court permitted dam height upto
EL 90.0 m with 3.0 m hump. The target achieved
on 31.12.2000. Honourable Supreme Court gave its
final judgement regarding writ petition field by NBA.
12 04.12.2000
Water supply has been started for drinking water.
13 10.02.2001
Drinking water supply started through IBPT.
14 17.05.2002
NCA (Narmada Control Authority) approved the
dam height upto EL 95.0 m with 3.0 m hump in
its 61st meeting held at New Delhi. The target
achieved on 15.07.2002.
15 20.08.2002
Water flow started in Main Canal through Right
Tunnel of IBPT (Irrigation Bye Pass Tunnel).
16 13.03.2003
Both Tunnels of IBPT in operation.
17 14.05.2003 NCA permitted to raise dam height from 95 to 100 mts.
18 04.07.2003 Work of raising of dam height upto 100 mt. completed
19 16.03.2004 NCA permitted to raise dam height from 100 to 100.64 mt.
20 30.06.2004 Work of raising dam height upto 110.64 mt. completed.
21 24.08.2004 Canal Head Power House commissioned.
22 01.02.2005 First unit of River BEd Power House is commissioned
23 05.03.2005 35 VSAs are handed over to the respective WUAs for participatory Irrigation Management.
24 07.03.2005 Work of Botad Branch Canal started