|
|
|
|

|
| -
Is Water availability over estimated ? |
|
The
availability of water in Narmada river has been assessed in
the most sophisticated and systematic manner in consultation
with the Central Water Commission (CWC), the highest expert
technical body of the nation by utilizing rainfall series from
1891 to 1992 and actual river flow series from 1948 to 1992.
The actual river flow series for 45 years is not adequate for
planning mega-project with a life of more than 100 years and a
large catchments with co-efficient of annual flow variations
of 0.35 which may need minimum 130 years data of both rainfall
and river flows. Therefore combined actual and hind cast
available data of about 100 years is used as per international
standard practice. Based on this method, 75% dependable
availability is 27.22 MAF and not 22.69 MAF estimated by the
critics. Even the World Bank in its detailed scrutiny while
extending financial assistance had accepted and endorsed these
calculations.
|
Design
Floods, Observed Highest Floods and Revised Spillways
for Some Projects in Gujarat |
River
Valley
Projects |
Total
Catchment Area (sq.km) |
Spillway
Design Flood as per Project Report (Cumecs) |
Highest
Observed Flood (Cumecs) |
Revised
Spillway (Cumecs) |
| Dharoi |
5485.84 |
11213.00 |
14150.00 |
21662.00 |
| Dantiwada |
2862.00 |
6654.00 |
11950.00 |
18123.00 |
| Machhu-I |
735.00 |
3313.00 |
9340.00 |
5947.00 |
| Machhu-II |
1928.71 |
5663.00 |
16307.00 |
20925.00 |
| Damanganga |
1813.00 |
11100.00 |
12900.00 |
12854.00 |
| Source:
Narmada, Water Resources & Water Supply Dept., GoG |
| This
experience shows that in most of the projects, flood
greater than the design flood has been observed,
consequently requiring revision of the spillway design
at a later stage. This shows that the assessment of
dependable flow has been made on a realistic
conservative side. |
|
| |
| -
Is it not possible to find a technical alternative to Sardar
Sarovar Project ? |
|
From technical
considerations like dependability, carry over storage, flood
control, power generation, submergence, evaporation, life span
(serviceability) and social considerations like equity in
distribution, Sardar Sarovar Project has practically no
alternative. According to a World Bank report on Sardar
Sarovar Project, even if it were technically possible (which
it is not), to find enough small tank sites, to hold the same
amount of water, the land lost due to inundation, could well
be over 1.0 M ha. against 37,000 ha. for Sardar Sarovar
Project. The area where Narmada canal waters are going is one
of the least rains receiving areas. Secondly, even if we
construct such small tanks/dams, how will they be filled in
the absence of regular, adequate and dependable rainfall which
is an exception than a rule in most of the western India? |
| |
-
It is feared that command area of the project would suffer
from water logging and
salinity of soil would come to surface, making land
unfit for cultivation. |
|
Water logging
due to excessive ground water accumulation can be a side
effect of canal irrigation over a long period. It can be
prevented by appropriate water management practices. In the
SSP, following specific measures have been built in
the system, and would ensure that there would not be any
problem of water logging or salinity surfacing :-
-
Lining main
canal, branches and entire canal net work upto 8 ha. block
to minimize seepage.
-
Limited
water delta of 53 cm (21’’) against normal 75 cm in
existing projects.
-
Simultaneous
command area development.
-
Conjunctive
use of surface and ground water.
-
Remote
Controlled Automatic Canal Operation.
-
Volumetric
and rotational water supply by Wara bandhi.
-
Water
application allowance based on agro-climatic zoning.
-
Better
water management practices and active participation of
farmers.
|
| |
-
Irrigation efficiency assumed is unrealistic and hence actual
coverage of irrigation
would be lesser ! |
|
This
apprehension is unfounded. Water management aspects mentioned
earlier, and particularly computerized automatic control and
volumetric distribution of water, supply of water to groups of
farmers and not individual, would help attain better
efficiency. Gujarat has proved efficiency in water management
under conventional system also, by capturing national
productivity award for five consecutive years. |
| |
| -
The Project will not solve the drought problem of Kutch and
Saurashtra. |
|
The Project
will provide irrigation to 0.543 million hectares of land in
Saurashtra and 0.113 million hectares in Kutch district.
Besides this, the drinking water supply would be made to most
of the water scarce regions of Kutch and Saurashtra. A special
outlay of US $ 500 millions has been made in the 9th Five Year
Plan for the implementation of water supply projects. 32 works
costing 6.22 billion rupees (~US $ 156 million) for Saurashtra
Branch Canal have been taken up and they are planned to be
completed by December, 2000. The Kutch Branch Canal is planned
to be taken up during 2000-2001.
On completion of the canals of Saurashtra and Kutch regions in
SSP, it is anticipated that present actual irrigation in
Saurashtra region from existing schemes will be about five
times while for Kutch region it would be more than three times
than present actual irrigation. |
| |
-
Sugar factories are sanctioned in command and thus water will
not reach distant
areas of North Gujarat, Saurashtra and Kutch. |
|
There are
existing 14 sugar factories in Gujarat. All of them are
outside the command of SSP. Two factories are under
consideration in the command area at Amod and Karjan, but no
guarantee or assurance has been given for supply of water for
sugarcane for these factories from SSP, as it does not supply
water for irrigation in summer. Even the quantum of 53 cm or
21 inch delta will not be adequate for sugarcane. Since water
would be given to groups of farmers for a block on volumetric
basis, there would not be scope for water intensive crops like
sugarcane or banana, unless drip irrigation or similar water
saving technology is adopted. If water saving technology is
adopted with same delta, the question of crop becomes
irrelevant. |
| |
| -
Will the SSP River Bed Power House be redundant as the time
passes ? |
|
During the
final stage when Madhya Pradesh would be utilising its entire
18.25 MAF of water, the SSP River Bed Power House will not be
redundant as it is proposed to operate the underground River
Bed Power House as reversible turbine units, by pumping water
from the downstream Garudeshwar weir during the non-peaking
hours. During the peaking hours i.e. 3 hours in the morning
and 3 hours in the evening, this water shall be utilised for
generating peaking power of 1200 MW. Question of underground
power house becoming redundant, therefore, does not arise as
it will be based on recirculation of water. In addition to
this, 250 MW from the canal head
power house would also be available as peaking power when the
9.5 MAF water will be passed through the canal head power
house. |
| |
| -
Is it true that the SSP will consume more power than it is
likely to produce? |
|
In no way the
Project can consume more power than it is likely to generate.
In fact in SSP, the total power generation at installed
capacity will be 1450 MW, more than 18% of the total present
installed capacity of the State. Perhaps this misconception
is because of the reversible pump turbines in RBPH. In fact,
reversible turbines - 6 units of 200 MW each have been
proposed to generate off peak energy by utilizing the surplus
energy available during night. On the contrary, this will
provide valuable peaking energy to the western grid which is
in deficit of peaking energy by 3700 MW and therefore the
Central Electricity Authority (CEA) of Govt. of India has
approved this Project as part of its least cost expansion
programe. |
| |
-
Is it really ever possible to successfully relocate and
rehabilitate such a large human
population? |
|
Percentage of
area submerged to area irrigated is 1.65% in the Sardar
Sarovar Project, compared to 4 to 5% in many projects in the
country and around the world. The ratio of Project
beneficiaries to Project affected persons stands as high as
100:1.
|
Details
of Submergence under Sardar Sarovar Project |
|
Type
of Land |
|
State |
| Gujarat |
Maharashtra |
Madhya
Pradesh |
|
Total |
| Cultivable
Land |
1877 |
1519 |
7883 |
11279 |
| Forest |
4166 |
6488 |
2731 |
13385 |
| Other
land including river bed |
1069 |
1592 |
10208 |
12869 |
| Total |
7112 |
9599 |
20822 |
37533 |
|
Counting
each major son as a separate unit, 40,827 families would
be displaced, out of which 9,063 families have been
resettled till February, 2001.
Incremental approach (pari passu) to resettlement.
In addition to the earlier property compensation focus
for the R&R, now the people centered development
focus has been developed.
For the first time in the Country, the concept of land
for land (minimum 2 ha) is prescribed and this benefit
is extended even to joint holders, landless laborers,
encroachers etc. Adequate monetary benefits. Minimum infrastructure
facilities like roads, schools, health
services etc. are provided at rehabilitation sites. Sustainable
income generating packages.
|
|
|
|
 |