| RELEVANT
EVENTS AFTER APPOINTMENT OF NARMADA WATER DISPUTES TRIBUNAL |
- 16th
August, 1978
Final Order and Decision of the Tribunal.
|
- 1978
- State of
Madhya Pradesh sought clarification as to why the height
of Navagam dam was 455 ft, and as to carry over capacity
of Navagam dam and proposed setting up of Construction
Advisory Committee.
- State of
Gujarat sought clarification regarding operation period of
certain clauses of the Final Order and Decision, sharing
of costs and benefits, completion of Narmada Sagar Dam
concurrently with or earlier than construction of SSP, and
functioning of Review Committee.
- State of
Maharashtra sought clarification regarding period of
operation of certain clauses of the Final Order and
Decision, and sharing of costs.
- State of
Rajasthan sought clarification regarding utilisation of
surplus water and apportionment of cost of canal.
- Union of
India sought clarification regarding :
- Utilisation
of surplus water.
- Acquisition
of buildings situated between FRL 455 ft and MWL 460 ft
and including back water effect. regarding directions for
effective functioning of Narmada Coastal Authority.
- For guidance
regarding modalities of taking final
decisions expeditiously by the Review Committee.
|
- 7th
December, 1979
Further Report by Tribunal under Sec. 5(3) of the
Inter-State Water Disputes Act, 1956, on the
clarifications sought by the party-States and by Union of
India.
|
- 12th
December, 1979
Final Order and Decision of the Tribunal published in
Gazette.
|
|
|
 |