The Dholka branch
canal of the Sardar Sarovar Project, 71.380 km long off takes at
ch. 246.366 km of the Narmada main canal near village Jaspur of
Kalol taluka of Gandhinagar district. 92 villages are partly or
totally covered for irrigation. Its discharge capacity at head is
53.62 cumecs, while at tail it is 4.911 cumecs. The cross-section
of this branch canal at head is 6.50 m X 3.40 m while at tail is
2.0m X 1.60 m.
Total 45637
ha command area of Daskroi, Dholka and Sanand talukas of Ahmedabad
district, Kalol taluka of Gandhinagar and Tarapur taluka of Anand
districts will be benefited by irrigation.
Details of command
area are given as under :-
|
Sr.
No.
|
District
|
Taluka
|
Nos
of Villages
|
CCA
in Ha.
|
|
1
|
Ahmedabad
|
Daskroi
|
16
|
4510
|
|
2
|
Ahmedabad
|
Dholka
|
43
|
26349
|
|
3
|
Ahmedabad
|
Sanand
|
19
|
10825
|
|
4
|
Gandhinagar
|
Kalol
|
13
|
3807
|
|
5
|
Anand
|
Tarapur
|
1
|
122
|
|
|
Total
|
5
Nos.
|
92
|
45613
|
Dholka branch
canal passes through Daskroi, Dholka and Sanand taluka of Ahmedabad
district, Kalol taluka of Gandhinagar district. The works of earth-work
and structure have been completed in August 1997. The work of cement
concrete lining is completed up to 80% and remaining work will be
completed shortly. The works of distribution system are also taken
up on hand and planned to be completed by 2007-08.
Water for irrigation
in the SSP will be conveyed through a 66000 km network of conveyance
and distribution system consisting of branch canals, distributaries,
minors and sub-minors. It may be mentioned here that total 44 branch
canals having length of 2528 km are off taking from the Narmada
main canal and out of which the work of 1300 km length is completed.
Total 690 distributaries having length of 5485 kms off take from
these 44 branch canals, out of which the works of 1500 km length
are completed.
|