THESAURUS
  • Terminal Major Dam :
    The major dam constructed on the river beyond that no such dam can be planned to construct.
  • Contour Sheets :
    Plans showing the natural levels of ground.
  • NWDT :
    Narmada Water Dispute Tribunal.
  • R.L. :
    Reduced Level.
  • Spillway Gates :
    Gates provide at overflow zone of the dam.
  • Chute Spillway :
    A Long ****** at pts of gates which enables the flow racing on rocky river bed.
  • Service Spillway :
  • Spillway Capacity :
    It is the capacity which is balancing the inflow minus storage of FRL
  • F.S.L. :
    Full Supply Level
  • H.R. :
    Regulator at the head end of the canal.
  • F.S.D. :
    Full Supply Depth.
  • Design Discharge Capacity :
    Designed (predetermined) water carrying capacity of canals OR maximum safe discharge capacity of canal.
  • Branches :
    The off taking canals from main canal.
  • Distribution system :
    The off taking canals from the main canal.
  • River bed Power House :
    Electric power house constructed to generate electricity at river bed using water stored in reservoir.
  • Cumec :
    Cubic meter per second.
  • MAF :
    Million Acre feet.
  • FRL :
    Full Reservoir Level.
  • Draw down Level :
    Fall of the water level in the canal.
  • Concrete Gravity Dam :
    Obstruction created across the river george portion using cement concrete to store water on upstream side.
  • Chute spill Radial Gates :
    Water opening in the form of radial shapes provided at chute spillway.
  • Sluices :
    Opening provided at the bottom part of dam to release water during the lean season to impart benefit to the down stream side.